Oracle Invokes Force Majeure on New Mexico AI Data Center
By @sharedot · · 7 pages
- Business
- Oracle
- Blue Owl
- Data Centers
- Stargate
Oracle sent a force majeure notice on its Project Jupiter campus in New Mexico to protect itself if the 2028 launch slips, sending ORCL down about 4–5%.
What happened
On Thursday, September 24, 2026, Oracle sent a force majeure notice to the developer of its New Mexico data center campus, known as Project Jupiter, a unit of Blue Owl Capital, CNBC confirmed.
According to CNBC, the notice lets Oracle defer payments on the campus if it fails to come online as expected in 2028. Oracle told CNBC that "Project Jupiter remains on our planned schedule" and that the company is "fully committed to New Mexico and confident in our path forward."
Blue Owl said in its own statement to CNBC that the notice "does not change the financial commitments to this multi-year project."
Why it surprised the market
Investors read the notice as a signal that the 2028 timeline is at risk, because companies rarely invoke force majeure on projects running smoothly.
TradingNEWS reports that Oracle shares fell as low as $133.48 before recovering to $137.45, down 4.9% on the day, its steepest intraday drop since the September 10 earnings reaction. The stock trades 57% below its all-time closing high of $324.63 set in September 2025.
Blue Owl was also hit hard: AOL reports OWL traded at $9.20, down 4.22% on the session and down roughly 47% over one year.
The power problem behind the delay
According to TradingNEWS, the root cause is power: the campus is designed to run on up to 2.45 GW of Bloom Energy fuel cells that need natural gas from a 17-mile pipeline that doesn't exist yet.
That pipeline's completion has slipped from August 2026 to February 2027 after the New Mexico State Land Office repeatedly refused right-of-way permits across state trust lands. Without gas, the fuel cells cannot run and the campus has no viable power source.
Bloom Energy shares fell 6.52% on the news, per TradingNEWS.
The stakes: an $18 billion loan and Stargate
CNBC reports the project carries $18 billion in debt tied to the data center, which the Financial Times says is already trading at stressed levels.
TradingNEWS details that 20 financial institutions assembled that lending package, which sits with the developer rather than Oracle, while Blue Owl owns Stack Infrastructure and supplies the equity. Project Jupiter is part of the broader Stargate AI infrastructure program with OpenAI and SoftBank.
AOL also notes private credit default rates hit a record 6.3% in the 12 months through August, per CNBC, heightening sensitivity to any lender stress in the AI buildout.
What comes next
Oracle co-CEO Clay Magouyrk told analysts on the September 10 earnings call that Project Jupiter would not affect the company's fiscal 2027 revenue or earnings guidance, CNBC reports.
The company's Q1 FY27 results showed revenue up 30% to $19.3 billion, cloud infrastructure revenue up 121% to $7.4 billion, and remaining performance obligations of $664 billion, per TradingNEWS.
Watch for an 8-K from Blue Owl disclosing its specific New Mexico exposure — AOL flags that such a disclosure, or a sustained break below $9.00 for OWL, would signal how the market ultimately prices the risk.